| No | Tanggal | Jenis Kegiatan | Pemasukan | Pengeluaran |
| 1 | 28 Februari 2020 | Infaq (KA) | 10,000,000.00 | |
| 2 | 2 Maret 2020 | Belanja Galvalum | 5,256,000.00 | |
| 3 | 2 Maret 2020 | Belanja Keramik | 1,588,000.00 | |
| 4 | 2 Maret 2020 | Belanja Bata, Pasir, Semen | 1,695,000.00 | |
| 5 | 2 Maret 2020 | Belanja Gamping | 110,000.00 | |
| 6 | 8 Maret 2020 | Infaq (KA) | 10,000,000.00 | |
| 7 | 8 Maret 2020 | belanja besi dan papan utk musholla dau | 1,421,000.00 | |
| 8 | 14 maret 2020 | belanja pasir, semen dll | 2,534,000.00 | |
| 9 | 14 maret 2020 | Ongkos Tukang | 2,350,000.00 | |
| 10 | 16 maret 2020 | semen; pasir | 2,385,000.00 | |
| 11 | 17 maret 2020 | Infaq (KA) | 10,000,000.00 | |
| 12 | 17 maret 2020 | Infaq (I.Z.) | 20,000,000.00 | |
| 13 | 17 maret 2020 | Tambahan infaq | 2,500,000.00 | |
| 14 | 17 maret 2020 | bendrat | 33,000.00 | |
| 15 | 17 maret 2020 | belanja besi 1 | 4,656,250.00 | |
| 16 | 18 maret 2020 | belanja besi 2, paku | 7,206,000.00 | |
| 17 | 19 maret 2020 | kayu basiya | 750,000.00 | |
| 18 | 19 maret 2020 | triplek 9mm | 880,000.00 | |
| 19 | 21 maret 2020 | Sesek Bambu | 640,000.00 | |
| 20 | 21 maret 2020 | Beli Batu Kali 2 x | 2,900,000.00 | |
| 21 | 21 maret 2020 | Ongkos Tukang | 2,250,000.00 | |
| 22 | 22 maret 2020 | Besi 12 | 1,446,000.00 | |
| 23 | 23 maret 2020 | Belanja besi | 4,500,000.00 | |
| 24 | 23 maret 2020 | Belanja Batu Bata merah 1000, bodem | 1,340,000.00 | |
| 25 | 23 maret 2020 | Belanja pasir, semen, gamping, koral dll | 4,193,000.00 | |
| 26 | 25 maret 2020 | Infaq KA | 20,000,000.00 | |
| 27 | 27 maret 2020 | Infaq Okky | 1,000,000.00 | |
| 28 | 28 maret 2020 | Ongkos Tukang | 2,530,000.00 | |
| 29 | 1-Apr-20 | Mas Ar Jkt | 700,000.00 | |
| 30 | 31 maret 2020 | Mb Endang | 500,000.00 | |
| 31 | 2-Apr-20 | Batako 1000 | 3,500,000.00 | |
| 32 | 2-Apr-20 | Koral 1 truk | 1,500,000.00 | |
| 33 | 2-Apr-20 | Pasir lumajang 1 truk | 1,500,000.00 | |
| 34 | 3-Apr-20 | pensil, kikir, selang | 64,000.00 | |
| 35 | 3-Apr-20 | kayu basiya | 750,000.00 | |
| 36 | 3-Apr-20 | Semen | 1,530,000.00 | |
| 37 | 3-Apr-20 | Sesek Bambu | 650,000.00 | |
| 38 | 3-Apr-20 | Tambang, perlengkapan | 80,000.00 | |
| 39 | 4-Apr-20 | Ongkos Tukang | 2,530,000.00 | |
| 40 | 4-Apr-20 | sak bekas | 150,000.00 | |
| 41 | 4-Apr-20 | gergaji besi, gerinda | 86,000.00 | |
| 42 | 5-Apr-20 | Transport | 200,000.00 | |
| 43 | 4-Apr-20 | kawat | 45,000.00 | |
| 44 | 4-Apr-20 | pipa PVC | 2,121,000.00 | |
| 45 | 5-Apr-20 | ArtCo dan Ap boot, sarung tangan dll | 820,000.00 | |
| 46 | 6-Apr-20 | Kabel dan solasi | 706,500.00 | |
| 47 | 7-Apr-20 | triplek 9mm | 570,000.00 | |
| 48 | 8-Apr-20 | Pasir lumajang dan semen 10 sak | 805,000.00 | |
| 49 | 9-Apr-20 | Infaq Dedy Eryanto | 500,000.00 | |
| 50 | 10-Apr-20 | Infaq N Elmizan | 650,000.00 | |
| 51 | 10-Apr-20 | Infaq Aida Nuraini | 300,000.00 | |
| 52 | 11-Apr-20 | Sewa Molen | 300,000.00 | |
| 53 | 11-Apr-20 | Keranjang Cor | 100,000.00 | |
| 54 | 11-Apr-20 | Semen Gresik | 612,000.00 | |
| 55 | 11-Apr-20 | Besi 10, 8, 6 50 btg | 5,412,500.00 | |
| 56 | 11-Apr-20 | Ongkos tukang dan pembuat batas longsoran tanah (6 hari) | 2,530,000.00 | |
| 57 | 11-Apr-20 | Konsumsi santri (cor) dan transport | 250,000.00 | |
| 58 | 11-Apr-20 | Dana Infaq K A | 25,000,000.00 | |
| 59 | 11-Apr-20 | Dana Infaq Doni | 2,600,000.00 | |
| 60 | 11-Apr-20 | Tanah Urug | 250,000.00 | |
| 61 | 11-Apr-20 | Besi 6, 8, 10 | 5,412,500.00 | |
| 62 | 13-Apr-20 | Sewa Kayu Penahan Cor | 800,000.00 | |
| 63 | 14-Apr-20 | Pasir | 1,500,000.00 | |
| 64 | 15-Apr-20 | kayu & triplek 9mm 12 bh | 3,200,000.00 | |
| 65 | 15-Apr-20 | transport | 150,000.00 | |
| 66 | 16-Apr-20 | Infaq RNA | 1,000,000.00 | |
| 67 | 16-Apr-20 | Besi 16, 12 | 1,802,500.00 | |
| 68 | 16-Apr-20 | Transport | 200,000.00 | |
| 69 | 17-Apr-20 | Kayu basiya 10 | 1,500,000.00 | |
| 70 | 18-Apr-20 | Ongkos tukang | 2,530,000.00 | |
| 71 | 19-Apr-20 | Bambu | 700,000.00 | |
| 72 | 20-Apr-20 | Stempel | 80,000.00 | |
| 73 | 22-Apr-20 | Triplex 9 mm 15 | 1,575,000.00 | |
| 74 | 25-Apr-20 | Ongkos Tukang | 2,260,000.00 | |
| 75 | 26-Apr-20 | Infaq Mb Har dan Ibu Z | 1,100,000.00 | |
| 76 | 27-Apr-20 | Besi 16; 12; 10; 8; bendrat | 7,494,000.00 | |
| 77 | 27-Apr-20 | Infaq Sigit dr. Smada | 2,000,000.00 | |
| 78 | 28-Apr-20 | Infaq M Yuski | 3,000,000.00 | |
| 79 | 29-Apr-20 | Nurul Hayat | 2,550,000.00 | |
| 80 | 29-Apr-20 | Semen 50 sak | 2,550,000.00 | |
| 81 | 29-Apr-20 | Semen 10 sak | 510,000.00 | |
| 82 | 29-Apr-20 | Kabel Ties | 10,000.00 | |
| JUMLAH | 113,400,000.00 | 109,999,250.00 | ||
| SISA SALDO | 3,400,750.00 | |||